AS/NZS 3012/2019+A1 BTS SwitchBoards

Post Reply
Slovett
Posts: 73
Joined: Mon Apr 13, 2020 9:26 pm
Has thanked: 31 times
Been thanked: 1 time

AS/NZS 3012/2019+A1 BTS SwitchBoards

Post by Slovett »

Hi,
Im just having a read through 3012:2019 to preempt some of the proposed changes coming for Domestic Construction SwitchBoards (BTS).

J3 (h) & (i) are self explanatory (Board must be 1200mm from ground and fixed into position with 2 stays) BUT is the 3.0m pole (for underground mains) mandatory or a guideline only? (Table J1)

Thanks
AlecK
Posts: 914
Joined: Thu Apr 16, 2020 11:24 am
Answers: 5
Has thanked: 2 times
Been thanked: 352 times

Re: AS/NZS 3012/2019+A1 BTS SwitchBoards

Post by AlecK »

currently "3012" is not cited as mandatory [ESR 25].
I am not aware of any suggestion that this will change when the citation in Schedule 2 changes to the newer edition.
That makes the entire document advisory.

App J is stated to be "normative"; and the effect of this is that it has the same status as the main text.
So a 'shall" statement in the appendix must be complied with in order to comply with the Standard as a whole.

However Table J1 has the word "typical" in the title; and nothing? in any clause makes any specific items on the Table mandatory,
so it can't be anything more than guidance.
These users thanked the author AlecK for the post (total 2):
Dan L (Fri May 28, 2021 10:24 am) • Slovett (Mon May 31, 2021 9:45 am)
Rating: 33.33%
Post Reply